Construction Underway at DUSD

If you’ve visited the district office of the Duarte Unified School District lately, you have seen for yourself that the promise of the future has already arrived. The modern design of the remodeled lobby matches the bold academic renaissance taking place throughout the district.

 

The updates to the district office, started in December 2016, are funded by Developer Fees, not Measure E Bond dollars or General Fund sources. Developer Fees can only be allocated to pay for facility improvement projects. They cannot be spent on other items like supplies, salaries or programs.

 

The Board of Education did approve the expenditure of Measure E funds to begin modernization projects to accommodate the transition to K-8 models in accordance with the district's Facilities Master Plan and Competitive Advantage Plan.

 

Andres Duarte, Beardslee, Maxwell and Royal Oaks will be remodeled to become K-8 campuses. Interim classrooms will be installed adjacent to Duarte High School to house 8th grade students for the 2017-18 school year that will be called the 8th Grade Village. 



These projects will be funded by Bond Measure E that was approved by the voters in November 2010. The Board of Education authorized Measure E funds, in the amount of $20 million, be available for these projects at the Board Meeting held on February 16, 2017.
 

Duarte USD has contracted architect Jay Tittle of the Little Diversified Architectural Consulting firm for these projects and the district’s Facilities Master Plan.

 

Future projects include a culinary arts classroom expansion and a sports complex at the campus of Duarte High School to be funded through the state school improvement bond which was approved by the California voters in November 2016.

 

View the estimated timeline phases for each project below:

 

  
  Andres Duarte Plan
Phase I
Site work at Central Avenue parking lot and student drop-off/pick-up. Open date: August, 2017

Phase II

Modernization of existing buildings to create science labs, music room, and locker rooms. Site work to add staff parking. Open date: August 2018
 
View full page image of the Andres Duarte modernization plans here
 
 
 
 
Beardslee
 
 
Phase I

Construction of 4 new classrooms with restrooms, site work and new amphitheater. Estimated Open Date: December, 2017

Phase II

Modernization of existing buildings to create science labs, music room, and locker rooms. Estimated Open Date: August, 2018

View full  image of the Beardslee modernization plans here
 
 
 
  
Maxwell Plan

 

Phase I

Construction of 4 new classrooms with restrooms and site work. Est. open date: December 2017

Phase II
 
Modernization of existing buildings to create science lab, music room, and locker rooms. Estimated Open Date: August 2018
 
View full  image of the Maxwell modernization plans here.  
 
 
 
  
 
Royal Oaks Plan  

 Phase I

Construction of 14 new classrooms with restrooms, site work, and additional parking lot with new exit to Royal Oaks Drive. Estimated Open Date: August, 2017

Phase II

Modernization of existing classrooms to create science labs, music rooms and locker rooms. Estimated Open Date: August, 2018

 View full  image of the Royal Oaks modernization plans here.  
 
 
 

8th Grade Village Plan

8th Grade Interim Village

Installation of 12 modular classrooms in the Duarte High School staff parking lot for the 2017-2018 school year.       

Convert the PLC to administration space for the Village.
Estimated Open Date: August, 2017
 
View full  image of the 8th Grade Village modernization plans here.   
 
 
 
 
 
 
 
  
DHS Culinary Arts Plan
 
Duarte High School Culinary Arts Plan
 
Expansion and improvement of the culinary arts classroom space. Estimated Open Date: August, 2018 
 
 
 View full page image of the Culinary Arts modernization plans here.
 
 
 
 
 
 
 
 
DHS Sports Plan  

Duarte High School Sports Complex

Modernize and air condition existing gymnasium. Add lobby with restrooms, ticket sales and snack bar to gym.

Relocate tennis courts. Modernize both locker rooms to add team rooms. Improve sports fields and access road west of gym. Estimated Open Date: TBD
 
 View full page image of the Sports Complex modernization plans here.
 
 